Master Plan Projects

The City Campus Master Plan comprises a number of distinct projects, which will be delivered on a staged basis from December 2009. These projects are a mixture of new buildings, significant refurbishments and internal upgrades.
The 3D model above shows all major projects. You can download a printable version [PDF, 509kb] of this model.
| Project | Description | Status | Timeframes* |
|---|---|---|---|
| Multi-Purpose Sports Hall | Underground sports hub at the heart of UTS. First facility to open under the Master Plan |
Complete. Opened May 2011 |
2009 to 2011 |
| Yura Mudang Housing | A 720-bed residential tower for UTS students, rising above existing Building 6 | Complete. Opened July 2011 | 2009 to 2011 |
| Great Hall Upgrade | Reinvention of UTS's principal ceremonial venue | Complete. Opened December 2011 |
2010-2011 |
| Building 6 Podium Extension | New teaching and learning spaces in Building 6, levels 3-7 | Complete. Opened March 2012 | 2011 to 2012 |
| Dr Chau Chak Wing Building | New building for the UTS Business School designed by Gehry Partners LLP | Site excavation underway - commenced end 2011 | 2010 to 2014 |
| Broadway Building | New 'gateway' building, also known as Information Technology and Engineering Building | Construction started March 2012, due to complete end 2013. | 2010 to 2014 |
| Thomas Street Building | New building | Durbach Block Jaggers, in association with BVN Architecture, anounced as winners of the design competition | 2011 to 2014 |
| Buildings 1 and 2 Podium Extension | Extensions and upgrades | Lacoste Stevenson with Daryl Jackson Robin Dyke announced as winners of the design competition | under review |
| Library Retrieval System | Underground automate storage and retrieval facility for UTS library collection | Site excavation started early 2012 | 2012 to 2014 |
| Learning Commons | Relocated, upgraded UTS library | Design competition forthcoming | 2013 to 2016 |
| Revitalised Alumni Green | New campus heart | Pending completion of underground Library Retrieval System building | 2014 |
| Buildings 1, 3 and 4 | General refurbishment | To be advised | tba |
| Building 5 | General refurbishment | Pending completion of Building 14 | 2016 to 2018 |
| Building 10 | General refurbishment | Pending completion of new Broadway Building | 2010 to 2014 |
*NOTE: All project timeframes are indicative only and may vary as Master Plan projects progress.